Steed Residence

39 Budget      39 Schedule

Revisions to Original Plans - Change Orders

  Change Order Description Owner Approval Status

Supervisor Update

1 Widen downstairs hall to garage.  Reconfigure plan. Approved Complete

 

2 Plumbing, electrical and ventilation for washer and dryer in mechanical room Approved Unsure of completion status

3 Add corbels below beams Approved Sanding in process

4 Lower ceiling in master bedroom Approved Complete

5 Add hidden door to attic access above master bedroom Approved In Process

6 Bead board ceiling in kitchen Approved Complete

7 Upgrade air filters Pending Approval  

8 Change terrace stairs to wood from masonry Approved Complete

9 Revised kitchen cabinetry layout, door design, wood specification Approved Awaiting cabinet installer to adjust and 

10 Install t&g ceiling below exterior terrace Approved Approved - Complete

11 Install chimney caps Approved Approved - Complete

12 Install stone on walls at front entry Approved  Complete

13 Change cabinetry in Bath 2 to furniture piece Approved In Process

14 Install steel at interior stairs Approved Complete

15 Change electrical plan Approved Completed

16 Change trim material in studies Rejected  

17 Install safe in master closet Approved Safe purchased.  Awaiting installation.

18 Install trim on Master bedroom ceiling Approved  Complete

19 Sand Posts Pending  

 

20 Change Closets Pending Completed

 

 