Steed Residence
39 Budget
39 Schedule
Revisions to Original Plans - Change Orders
Change Order Description
Owner Approval
Status
Supervisor Update
1
Widen downstairs hall to garage. Reconfigure plan.
Approved
Complete
2
Plumbing, electrical and ventilation for washer and dryer in mechanical room
Approved
Unsure of completion status
3
Add corbels below beams
Approved
Sanding in process
4
Lower ceiling in master bedroom
Approved
Complete
5
Add hidden door to attic access above master bedroom
Approved
In Process
6
Bead board ceiling in kitchen
Approved
Complete
7
Upgrade air filters
Pending Approval
8
Change terrace stairs to wood from masonry
Approved
Complete
9
Revised kitchen cabinetry layout, door design, wood specification
Approved
Awaiting cabinet installer to adjust and
10
Install t&g ceiling below exterior terrace
Approved
Approved - Complete
11
Install chimney caps
Approved
Approved - Complete
12
Install stone on walls at front entry
Approved
Complete
13
Change cabinetry in Bath 2 to furniture piece
Approved
In Process
14
Install steel at interior stairs
Approved
Complete
15
Change electrical plan
Approved
Completed
16
Change trim material in studies
Rejected
17
Install safe in master closet
Approved
Safe purchased. Awaiting installation.
18
Install trim on Master bedroom ceiling
Approved
Complete
19
Sand Posts
Pending
20
Change Closets
Pending
Completed