Foundation Checklist

Supervisor Name

Project

Are we in possession of a copy of the concrete subcontractor's proof of general liability insurance certificate?

Has the concrete subcontractor signed a waiver of worker's compensation insurance?

Texas Workers Compensation Waver

Are we in possession of a copy of the plumbing subcontractor's proof of general liability insurance certificate?
Has the plumbing contractor signed a waiver of worker's compensation insurance?

Texas Workers Compensation Waver

Are we in possession of a copy of the electrical contractor's general liability insurance certificate?
Has the electrical contractor signed a waiver of worker's compensation insurance?

Texas Workers Compensation Waver

Does the concrete subcontractor have the latest set of architectural plans including all new revisions?   

Does the concrete subcontractor have the latest set of engineering plans including all new revisions?   

Does the plumbing subcontractor have the latest set of architectural plans including all new revisions?   

Has the engineer who designed the foundation been called to inspect the forms, beams and steel?

Do we have a clean inspection (in writing) from the engineer who designed the foundation?    

Has the architect been called to confirm the form dimensions, plumbing locations, & drops?

Have you confirmed that all tile locations are dropped?

Have you confirmed that all wood locations are dropped?

Have conduits been provided to all locations that are not accessible by framing (ex. Kitchen Islands)

Has a survey been ordered?

Does the survey confirm that the slab is situated precisely according to plan?

Has an inspection been performed of the rough plumbing?   

Are we in possession of the rough plumbing inspection showing no corrections to be made?

***Have you walked the job with the concrete subcontractor to check form dimensions, drop locations and dimensions and steel layout and spacing from compacted dirt prior to pour? 
***Have you walked the job with the plumbing subcontractor to check pipe locations (confirm dimensions), existence of circulation system, water heater locations, and in slab dryer vents? 
***Have you walked the job with the electrical subcontractor to check conduit locations, floor plug locations, and other in slab electrical issues? 
***Are we cleared from the engineer to pour - no items left to be corrected? 

 